VORWERK-ASA GmbH
Replacement of District Heating Line 60
The project ‘Replacement of District Heating Pipeline 60, Passendorfer Wiesen’ involved the construction of a new District Heating Pipeline 60 (supply line DN600/900 and return line DN600/800). As part of this construction work, a new bridge was built to cross the Ruder Canal, and the district heating pipeline was connected to the existing pipework.
Customer
Energieversorgung Halle Netz GmbH
Order Type
Joint venture
Construction time
01/2024 -
02/2026
COOL Gellersen
FRIEDRICH VORWERK completed the turnkey construction of a CO₂ liquefaction plant for processing carbon dioxide from a biogas treatment plant in Kirchgellersen. The plant produces up to 600 kg/h of high-quality, cryogenic liquid CO₂ and meets strict requirements for use in the food industry, including for mineral water.
Customer
Bioenergie Gellersen GmbH & Co. KG
Order Type
General contractor
Construction time
02/2023 -
06/2024
Kumasi 1 Thermal Power Project
The fuel gas supply plant for the Kumasi 1 Thermal Power Project (K1TPP) draws natural gas from the local grid, processes it, and reliably supplies a 250-MW gas-fired power plant with conditioned fuel gas, thereby strengthening the power supply and grid stability in the Ashanti Region. The scope of work included engineering, fabrication, transportation, and installation of the plant, which features redundant supply lines as well as systems for gas purification, measurement, preheating, and pressure regulation.
Customer
Volta River Authority-Corporate
Order Type
General contractor
Construction time
02/2023 -
12/2026
Gas treatment plant Halle-North sewage treatment plant
Gas treatment plant Halle-North sewage treatment plant
Customer
Hallesche Wasser und Stadtwirtschaft GmbH, Bornknechtstraße 5, 06108 Halle (Saale)
Order Type
General Contractor
Construction time
08/2019 -
02/2020
New construction of the Würselen compressor station
New construction of the Würselen compressor station
Customer
Open Grid Europe GmbH, Kallenberger Straße 5, 45141 Essen
Order Type
Consortium
Construction time
07/2019 -
11/2020
BGAA Bachenbülach
Biogas upgrading plant using the membrane process for 220m³/h raw biogas, with expansion preparation to 400m³/h
Customer
Energie 360 ° AG, Aargauerstraße 182, CH-8010 Zürich
Order Type
General Contractor
Construction time
03/2019 -
07/2019
Gas pre-cleaning Lot 1 + BGAA Lot 2 Sinsheim
AVR BioGas GmbH Biogas upgrading plant 900m³/h
Customer
AVR BioGas GmbH, Dietmar-Hopp-Str. 8, 74889 Sinsheim
Order Type
General Contractor
Construction time
08/2018 -
08/2019
BGAA (A) AVG Köln
BGAA amine scrubbing for 500Nm³h biogas with gas storage and flaring systems
Customer
Thoeni Industriebetriebe GmbH, Obermarktstraße 48, A-6410 Telfs
Order Type
General Contractor
Construction time
04/2018 -
11/2018
Conversion and relocation of CWH GDRM filter plant Legden
Plant modification, relocation of the filter and renewal of the pipes.
Customer
Open Grid Europe GmbH, Kallenberger Straße 5, 45141 Essen
Order Type
General Contractor
Construction time
01/2018 -
07/2018
Niederuzwil biogas upgrading plant
Treatment plant using a membrane on an AXPO-BGA. 350m³/h raw biogas. Gas storage, gas device, processing, counting and odorisation.
Customer
Energie 360 ° AG, Aargauerstraße 182, CH-8010 Zürich
Order Type
General Contractor
Construction time
08/2017 -